US-41 resurfacing project in Skandia begins April 1
March 31, 2025
ISHPEMING, Mich. - The Michigan Department of Transportation (MDOT) is investing about $5.2 million to resurface nearly 6 miles of US-41 from south of the M-94 east junction to north of Kunde Road in Marquette County. Work includes asphalt crushing, shaping and resurfacing; grading; drainage; guardrail; and pavement markings.
County:
Marquette
Highway:
US-41
Closest community:
Skandia
Tentative start date:
Signs and preliminary work begin Tuesday, April 1, 2025
Tree clearing begins Friday, April 4, 2025
Major work expected to begin Thursday, May 15, 2025
Project end date:
Monday, Sept. 15, 2025
Traffic restrictions:
One lane of alternating traffic will be open on US-41 using traffic regulators.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 50 jobs.
Safety benefit:
This work will extend the service life of the roadway to maintain a safe route for all users.