Houghton Lift Bridge Rehabilitation (CMGC)

Scope

US-41 and M-26 over Portage Lake, Houghton County. The scope of work includes deck replacement of one fixed approach span, deck and substructure patching, replacement of grid decking on the lift span, partial cleaning and coating of structural steel, structural steel repairs, pile cluster and fender repair, and electrical and mechanical upgrades.


Job number

212997

Control section

B01-31012

Delivery method

 CMGC

Contact

Talia Belill, Innovative Contracting Project Manager
517-230-6262

Estimated cost

Construction cost: $36,190,246

Anticipated schedule

Industry forum: April 2025

Issue request for qualifications (RFQ): May 2025

Statement of qualifications (SOQ): June 2025

Notification of selected submitter: June 2025

Preconstruction services contract award: July 2025

Construction: 2027-2028

Project attributes

DBE goal (preconstruction): 0%

DBE goal (construction): TBD

Anticipated prequalification

TBD