Houghton Lift Bridge Rehabilitation (CMGC)
Scope
US-41 and M-26 over Portage Lake, Houghton County. The scope of work includes deck replacement of one fixed approach span, deck and substructure patching, replacement of grid decking on the lift span, partial cleaning and coating of structural steel, structural steel repairs, pile cluster and fender repair, and electrical and mechanical upgrades.
Job number
212997
Control section
B01-31012
Delivery method
CMGC
Contact
Talia Belill, Innovative Contracting Project Manager
517-230-6262
Estimated cost
Construction cost: $36,190,246
Anticipated schedule
Industry forum: April 2025
Issue request for qualifications (RFQ): May 2025
Statement of qualifications (SOQ): June 2025
Notification of selected submitter: June 2025
Preconstruction services contract award: July 2025
Construction: 2027-2028
Project attributes
DBE goal (preconstruction): 0%
DBE goal (construction): TBD
Anticipated prequalification
Fa