30 kW and Larger Interconnection Procedures
Staff Contact: Julie Baldwin
Join MPSC-30KWANDLARGER Workgroup
The Commission's Order, dated February 27, 2007, directed the Engineering Section of the Commission's Operations and Wholesale Markets Division to convene a workgroup with these objectives:
- Identify reasonable and achievable interconnection time deadlines.
- Propose a system for determining whether interconnection costs are reasonable, actual costs.
- Study the impacts and benefits of requiring utilities to consult with transimission providers when certain interconnection applications are filed (for distribution-level interconnections).
- Investigate the impacts and benefits of requiring all generators to maintain an acceptable power factor.
- Develop criteria for identification of areas of opportunity for distributed generation on each utility's distribution system.
|
| |

 |
 |
General Information

 |  |
Meetings
 |
Proposals and Comments

 |
Documents
• Staff Report on Net Metering and Electric Utility Interconnection Issues, October 1, 2007 | • Appendix 1 to the Staff Report on Net Metering and Electric Utility Interconnection Issues, October 1, 2007 | • Appendix 2 to the Staff Report on Net Metering and Electric Utility Interconnection Issues, October 1, 2007 | • U-15113 Utility Interconnection Investigation Electronic Docket | • Staff Report on Utility Interconnection Issues, January 31, 2007 | • U-15113 October 24, 2006 Order | • U-15113 February 27, 2007 Order |
| |

 |