FAQ
|
 |
|
How do I get paid?
|
|
|
|
Answer:
|
|
Not more than once each month, the contractor shall submit to the architect an itemized application for payment, supported by such data substantiating the contractor's right to payment as the state may require. The form of application of payment shall be furnished by the state. The state will pay 100 percent of the amount due upon completion of each separate task or division of the contract on which the price is stated separately in the schedule of values. The architect may require for each application of payment, a consent of surety, waivers of lien from prime contractors, subcontractors and suppliers, as-built drawings, guarantees, manuals, brochures, operating instructions, or other documents, as required under the provisions of this contract for completed work. The payment will be made within 30 days after the architect has certified to the owner that work is in place in the portion of the facility covered by the applicable request for payment in accordance with the contract documents.
|
 |