Skip to main content

I-75/M-32 Interchange Rebuilding and Reconfiguration - Gaylord

About this project

Beginning in fall 2026, MDOT plans to replace the northbound and southbound I-75 bridges over M-32 in Gaylord and rebuild M-32 between Edelweiss Village Parkway/Meecher Road and Wisconsin Avenue. These bridges were built in 1961, are currently in poor condition and need to be replaced. This provides an opportunity to consider alternatives for this interchange that provide safe and efficient movement of people and goods through the Gaylord area and accommodate future increased traffic. Based on community input and engineering review, MDOT has selected a diverging diamond interchange (DDI) design for the I-75/M-32 interchange rebuilding project.

A DDI is an alternative interchange that improves safety, increases traffic flow and can reduce construction costs. They have been successfully implemented at several locations throughout Michigan in recent years, helping reduce crashes and congestion. To navigate a DDI, drivers follow signs, signals and pavement markings to cross to the left side of the roadway after the first set of traffic signals. Vehicles going straight proceed through a second set of traffic signals and cross back to the right side of the road. All left turns onto the freeway are free flowing.

In addition to rebuilding the interchange, this project will include:

  • Resurfacing M-32 between Murner Road and Meecher Road.
  • Building 5-foot-wide sidewalks on both sides of M-32 from South Townline Road to Little League Drive/Wilkinson Road, where it does not currently exist or is being removed during this project.
  • Building a 10-foot-wide sidewalk from the current path along Dickerson Road, through the DDI, to the 10-foot-wide North Central State Trail.
  • Installing a new traffic signal at the M-32/South Townline Road intersection.
  • Upgrading the traffic signals at the intersections of M-32/Meecher Road/Edelweiss Village Parkway and M-32/Dickerson Road.
  • Building a new MDOT carpool lot along Dickerson Road.
  • New interchange lighting for drivers and pedestrians.
  • Replacing the City of Gaylord’s watermain and sanitary sewer lines in the project limits.
  • Pedestrian amenities, including benches, decorative lighting and landscaping.
  • Improvements to local roads that will be used for detour routes during construction, including resurfacing McCoy Road between Dickerson Road and the I-75 Business Loop, and resurfacing Milbocker Road between South Townline Road and Dickerson Road.

Check Mi Drive for current lane closures

Know before you go!

Project details

Schedule

Fall 2026 - Fall 2028

Work is expected to begin in fall 2026 with construction of temporary traffic crossovers on I-75 north and south of the interchange, tree clearing and detour route improvements. In 2027, work will focus on replacing the northbound I-75 bridge and pavement, and rebuilding; M-32 east of West Street. In 2028, work will focus on replacing the southbound I-75 bridge and pavement, and rebuilding M-32 through the interchange and to the west. Landscaping is expected to occur in 2029.

Location

Gaylord

Otsego County

Cost

$54 million

Benefits

  • Improved safety
  • Improved traffic flow
  • Improved road and bridges

Lane/ramp closures and detours

Detour map
  • At least one lane of traffic will be maintained in each direction on M-32 at most times, except when the existing bridges are demolished and when new bridge beams are installed or some municipal utility replacement work is completed.
  • When M-32 is closed (for periods expected to last several days during demolition and beam placement), traffic will be detoured on South Townline Road, Milbocker Road/McCoy Road, and the I-75 Business Loop. This detour route will also be signed as a suggested alternate route for through-traffic during construction.
  • I-75 traffic will be maintained as much as possible using temporary pavement widening and temporary traffic crossovers.
  • Ramp closures will be staged to minimize traffic impacts, but detours will be required.
  • The Otsego County Road Commission plans to install a new roundabout at the McCoy Road/Dickerson Road intersection in 2026, expected to be complete before M-32 detours are required. 

Frequently asked questions (FAQs)

Stay connected

Media questions? Contact James Lake, Media Representative, at 906-250-0993.

  • Subscribe for email updates

    Get project updates delivered straight to your inbox.

  • Project questions?

    Brad Swanson, 989-731-5090
    Gaylord TSC