US-2 resurfacing east of Rapid River begins May 29
Contact: James Lake, MDOT Office of Communications, lakej1@michigan.gov 906-786-1830, ext. 311, Agency: Transportation
COUNTY: Delta
HIGHWAY: US-2
CLOSEST CITY: Rapid River
ESTIMATED STARTING DATE: Tuesday, May 29, 2012
ESTIMATED COMPLETION DATE: Thursday, Aug. 30, 2012
PROJECT: Resurfacing 4.5 miles of US-2 from Rapid River east to County Road 511. Work includes sidewalk ramp upgrades to be compliant with the Americans with Disabilities Act and bridge approach improvements. Paving is scheduled to begin in July.
TRAFFIC RESTRICTIONS: Lane closures with temporary signals and flag control.