All the ramps for I-94/US-131 are open and should remain open until next spring.
Lane/Ramp Closures:
Short-term lane closures will be used to place the remaining sound wall panels on westbound I-94 between Westnedge Avenue and US-131. The merge/weave lanes will be modified to standard ramps during the placement of the panels.
What work has been taking place?
The new westbound I-94 is open to traffic.
Construction of the sound walls is progressing on the north side of I-94 and foundations, posts, and panels are all being constructed. Trees are being removed on the south side of I-94 for the new sound wall.
Work on the new bridges over north- and southbound US-131 south of I-94 has begun and the bridges will take shape in the upcoming weeks and throughout the winter.
The eastbound I-94 bridge over 12th Street has been removed and will be reconstructed throughout the winter.
Cleanup is in progress and should be completed soon for the winter.
Who can I contact for more information?
You can contact Julie Hurley, MDOT Communications Representative, at 269-208-7829, or the Kalamazoo Transportation Service Center (TSC) at 269-375-8900. You can also visit the I-94 Widening and Reconstruction Web site at: www.michigan.gov/mdot94widening.