International Bridge maintenance diligence delays $80 million deck replacement; bridge financial challenges continue

Contact:  Phil Becker, International Bridge Administration, 906-635-5255, ext. 112
Agency: Transportation


August 20, 2008 - - The Joint International Bridge Authority (JIBA) Board of Directors received a very good report on the structural condition of the concrete bridge deck at its Aug. 20 meeting held in Sault Ste. Marie, Ont.

The consulting firm of Hardesty and Hanover presented the findings of a detailed inspection and structural evaluation of the bridge deck. It was anticipated the 45-year-old deck would have to be totally removed and replaced within the next 10-15 years, at an estimated cost of $80 million. However, the study found the deck to be in exceptionally good condition for its age.

The report recommends the blacktop overlay portion on the Canadian arch span to be replaced with a concrete overlay in 2009, costing approximately $2 million. It also recommends a concrete deck overlay of the entire bridge in 2023, costing approximately $24 million. The report suggests the deck replacement could be delayed until the mid 2040s.

"The bridge deck is in excellent condition due to the diligent preventive maintenance program in place at the International Bridge Administration (IBA)," said Phil Becker, IBA general manager. "Our IBA maintenance staff is to be commended for the great job they do to get the full service life out of the bridge deck."

Becker cautions, however, that despite good news, there remain significant financial challenges associated with the consultant recommendations for the deck overlays, when they are considered with other expected major bridge projects. Other major capital projects in the next 15 years include:

- 2011 - $11.7 million toll plaza redevelopment project to reduce traffic congestion between the U.S. Customs and Border Protection (USCBP) border station and the toll booths.
- 2014 - $4.7 million repainting of the Canadian arch span.
- 2018 - $9.0 million repainting of the U.S. arch spans.
- 2023 - $11.5 million repainting of the north approach spans and center girder spans.

"When we consider all of the combined costs for scheduled projects to keep the aging bridge and support facilities structurally sound and safe, we are looking at expending over $60 million in the next 15 years," says Becker. "Given that nearly $4.5 million of the $6 million annual toll revenue goes into the day-to-day operation and maintenance of the bridge, we have little opportunity to put funds in reserve to meet these future needs."

Becker also noted that the $60 million capital project program does not take into account the $40 million cost to replace the Canada Border Services Agency plaza, for which federal funding is being pursued.

The IBA is totally self-funded, based primarily on toll revenue, and receives no operational funds support from state, provincial, or federal government sources. Bridge traffic has dropped from 3.6 million annual crossings in 1994 to about 1.9 million crossings in 2007.

Sault Ste. Marie International Bridge: Bridging Our Past, Connecting Our Future
Link to Department and Agencies Web Site Index
Link to Statewide Online Services Index
Link to Statewide Web-based Surveys
Link to RSS feeds available on this site
Related Content
 •  MDOT announces transportation enhancement grants that will make improvements in seven Michigan counties
 •  MDOT to update public on US-41 construction plans, schedules in city of Menominee for 2010-11
 •  Gov. Granholm recognizes innovations by MDOT employees
 •  Ed Reavie honored for promoting the Mackinac Bridge and Straits area for over three decades
 •  MDOT reminds motorists that Freeway Courtesy Patrol is the only state-supported motorist assistance program
 •  MDOT to hold public meeting to discuss M-89 improvements in Otsego
 •  Slush holds clues for winter driving
 •  MDOT to hold US-127 BR public meeting in Isabella County
 •  Open house scheduled for Houghton streetscape project
 •  M-85 (Fort Street) bridge over Rouge River in Detroit to close over weekend for repairs
 •  Six of MDOT's 81 rest areas to close for winter
 •  M-22 detour begins Dec. 1 at Glen Lake Narrows in Leelanau County
 •  FEIS announced for the DRIC
 •  MDOT seeks public comment on draft 2009-2013 transportation program
 •  MDOT to host public meeting regarding 2010 sound wall construction at the I-94/US-24 interchange
 •  US-41/M-28 Michigamme curves project begins
 •  MDOT announces winter storm cleanup procedures on state highways
 •  Michigan earns high marks as a bicycle-friendly state
 •  I-75 Birch Run to Bridgeport reconstruction complete
 •  MDOT announces plans to accelerate connected vehicle technology research, testing and development in Michigan

Michigan.gov Home | MDOT Home | Site Map | FAQ | State Web Sites
Privacy Policy | Link Policy | Accessibility Policy | Security Policy | Michigan News | Michigan.gov Survey

Copyright © 2001-2008 State of Michigan