| LENGTHS |
| Total Length of Bridge (5 Miles) |
26,372 Ft. |
| Total Length of Steel Superstructure |
19,243 Ft. |
| Length of Suspension Bridge (including Anchorages) |
8,614 Ft. |
| Total Length of North Approach |
7,129 Ft. |
| Length of Main Span (between Main Towers) |
3,800 Ft. |
|
| |
| 8,038 Meters |
| 5,865 Meters |
| 2,626 Meters |
| 2,173 Meters |
| 1,158 Meters |
|
 |
 |
| HEIGHTS AND DEPTHS |
| Height of Main Towers above Water |
552 Ft. |
168.25 Meters |
| Maximum Depth to Rock at Midspan |
Unknown |
Unknown |
| Maximum Depth of Water at Midspan |
295 Ft. |
90 Meters |
| Maximum Depth of Tower Piers below Water |
210 Ft. |
64 Meters |
| Height of Roadway above Water at Midspan |
199 Ft. |
61 Meters |
| Underclearance at Midspan for Ships |
155 Ft. |
47 Meters |
| Maximum Depth of Water at Piers |
142 Ft. |
43 Meters |
| Maximum Depth of Piers Sunk through Overburden |
105 Ft. |
32 Meters |
|
| CABLES |
| Total Length of Wire in Main Cables |
42,000 Miles |
67,592 Kilometers |
| Maximum Tension in Each Cable |
16,000 Tons |
14,515,995 Kilograms |
| Number of Wires in Each Cable |
12,580 |
| Weight of Cables |
11,840 Tons |
10,741,067 Kilograms |
| Diameter of Main Cables |
24 1/2 Inches |
62.23 Centimeters |
| Diameter of Each Wire |
0.196 Inches |
.498 Centimeters |
|
 |
 |
| CONCRETE |
| Total Concrete in Bridge |
466,300 Cu. Yds. |
356,512 Cu. Meters |
| Total Concrete in Substructure |
451,000 Cu. Yds. |
344,814 Cu. Meters |
| Total Concrete in One Anchorage (No. 22) |
91,600 Cu. Yds. |
70,033 Cu. Meters |
| Total Concrete in One Pier (No. 19) |
80,600 Cu. Yds. |
61,623 Cu. Meters |
| Total Concrete in Superstructure |
15,300 Cu. Yds. |
11,698 Cu. Meters |
|
| WEIGHTS |
| Total Weight of Bridge |
1,024,500 Tons |
929,410,766 Kilograms |
| Total Weight of Concrete |
931,000 Tons |
844,589 Kilograms |
| Total Weight of Substructure |
919,100 Tons |
326,931,237 Kilograms |
| Total Weight of Two Anchorages |
360,380 Tons |
326,931,237 Kilograms |
| Total Weight of Two Main Piers |
318,000 Tons |
288,484,747 Kilograms |
| Total Weight of Superstructure |
104,400 Tons |
94,710,097 Kilograms |
| Total Weight of Structural Steel |
71,300 Tons |
64,682,272 Kilograms |
| Weight of Steel in Each Main Tower |
6,500 Tons |
5,896,701 Kilograms |
| Total Weight of Cable Wire |
11,840 Tons |
10,741,067 Kilograms |
| Total Weight of Concrete Roadway |
6,660 Tons |
6,041,850 Kilograms |
| Total Weight of Reinforcing Steel |
3,700 Tons |
3,356,584 Kilograms |
|
 |
 |
| RIVETS AND BOLTS |
| Total Number of Steel Rivets |
4,851,700 |
| Total Number of Steel Bolts |
1,016,600 |
|
| DESIGN AND DETAIL DRAWINGS |
| Total Number of Engineering Drawings |
4,000 |
| Total Number of Blueprints |
85,000 |
|
 |
 |
| MEN EMPLOYED |
| Total, at the Bridge Site |
3,500 |
| At Quarries, Shops, Mills, etc. |
7,500 |
| Total Number of Engineers |
350 |
|
| IMPORTANT DATES |
| Mackinac Bridge Authority Appointed |
June, 1950 |
| Board of Three Engineers Retained |
June, 1950 |
| Report of Board of Engineers |
January, 1951 |
| Financing and Construction Authorized by Legislature |
April 30, 1952 |
| D.B. Steinman Selected as Engineer |
January, 1953 |
| Preliminary Plans and Estimates Completed |
March, 1953 |
| Construction Contracts Negotiated |
March, 1953 |
| Bids Received for Sale of Bonds |
December 17, 1953 |
| Began Construction |
May 7, 1954 |
| Open to traffic |
November 1, 1957 |
| Formal dedication |
June 25-28, 1958 |
| 50 millionth crossing |
September 25, 1984 |
| 40th Anniversary Celebration |
November 1, 1997 |
| 100 millionth crossing |
June 25, 1998 |
|