Q 10. If my contractor cannot make bid item 23A because of the weather, can I use a modified original to substitute bid item C1 11?
|
|
|
|
Answer:
|
|
If the item (in this case C1 11) is not in the contract, then it is an extra by definition. You can never change the bid item by using a modified original. Remember to note the reduced use of 23A in your explanation of why you needed the extra.
|
 |