Q 5b. If the open graded drainage course aggregate base costs $4.32/syd and the existing dense graded aggregate base costs $3.32/syd and we are using 150,000 syd, do I submit the entire $648,000 or $150,000 the difference in cost between the two?
|
|
|
|
Answer:
|
|
You must always submit the entire amount for the extra item. Also, be sure to include the entire $648,000 when calculating the 6 percent or $48,000 Administrative Board limits. Be sure to mention the offsetting reduction in your Description of Changes field on FieldManager's Contract Modification general tab.
|
 |