A waiver should always be given by a contractor, subcontractor or supplier when payment is made. In simple terms, it is a receipt for payment. Most importantly, it announces to the homeowner that the construction lien rights are being relinquished - either in full (if full payment is received) or in part (if partial payment was received).
The owner, lessee or designee shall not rely on a full or partial unconditional or conditional waiver of lien provided by a person other than the lien claimant named in the waiver if the lien claimant has either provided a notice of furnishing under section 109 or is excused from filing the notice of furnishing under section 108 or 108A, unless the owner, lessee or designee FIRST verifies the authenticity of the lien waiver with the lien claimant, either in writing, by telephone or personally.
Waivers are legal documents and must use prescribed wording. To be considered legal documents, and to serve the purpose for which they were designed, use the appropriate type of waiver. Be certain that the waiver signed is appropriate to the situation.
A
Full Unconditional Waiver
states that full payment has been received and that there is no claim of lien against the homeowners' property.
Blank Forms (pdf):
Full Unconditional Waiver
PLEASE NOTE: INFORMATION PROVIDED INCLUDES CHANGES TO THE CONSTRUCTION LIEN ACT,
PURSUANT TO PA 497 OF 2006 AND PA 573 OF 2006.
|